Selasa, 06 Juni 2017

Tugas 2 Teknik Perawatan



Tanggal : 4 April 2017
Materi : ( Maintenance Costing ) / Biaya Pemeliharaan
Doni Indra D – 23414241 – 3IC09

Kerjakanlah soal – soal maintenance costing berikut ini !!
1.      To Calculate the mean time to repair (MTTR ) ?
a.       Eight Subsytem : a, b, c, d, e, f, g, h form an electronic system.
b.      The constants failure rates of these subsystems are :
la = 0.002 ,lb = 0.004 , lc = 0.006 , ld = 0.008 , le = 0.010 , lf = 0.012 , lg = 0.014 , lh = 0.016 failures per hour.
c.       The corresponding estimate corrective maintenance time are :
Ta = 2 hour, Tb =  3 hour, Tc = 4 hour, Td = 5 hour, Te = 6 hour, Tf = 7 hour, Tg = 8 hour, Th = 9 hour.

2.      Data historical of machine in industry :
a.       Hour ( 0 to 200) = up-time
b.      Hour ( 200 to 210 ) = down-time
c.       Hour ( 210 to 400 ) = up-time
d.      Hour ( 400 to 415) = down-time
e.       Hour ( 415 to 590 ) = up-time
f.       Hour ( 590 to 600 ) = down-time
g.      Hour (600 to 750 ) = up-time
To calculate of :
·         the mean time to between failure (MTBF ) and mean downtime (MDT) ?
·         the annual labor cost of corrective maintenance (CMal) ?
Whereas : SOH = 3500 hour, MTTR = 30 h, LCH = $ 40.

3.      Maintenance Cost-Related Data :
Description
Manufacture A system
Manufacture B system
Manufacture C System
Expected Life
15 years
15 years
15 years
Expected cost of  a corrective maintenance action
$2000
$2500
$3500
Annual failure rate
3 failures per year
3.5 failures per year
2.5 failures per year
Annual interest rate
4 %
4 %
4 %
Determine which of the three system will be less costly with present value of corrective maintenance ( Find the value of (PV)?
NB : Using the Formula II.

4.      Assume that we have the following time estimates to accomplish an activity :
OT = 85 days
PT = 105 days
MT = 90 days
To Calculate the activity expected duration time  ( Ta )?
           
5.      Assume that in maintenance organization we have the following data :
TAH = 2500 hour
BR = 0.2
LR = $25
N  = 50
To Calculate the cost per employee (Cem)and The total labor cost ( TLC )?



Jawaban :
1.  4x10-3 + 0,012 + 0,024 + 0,04 + 0,06 +0,084 + 0,112 + 0,144
                                     0,072
=  0,48 
   0,072
= 6,67

2.  a.MTBF
200 + 190 + 175 + 150
     4
= 178,75

MDT
10 + 15 + 10
          3
       = 11,66

                     b.= 3500 x 40 x 6,67
                         178,75
= 933800
    178,75                      
= 5224,06


3. MANUFACTURER A SYSTEM


      MANUFACTURER B SYSTEM


        MANUFACTURER C SYSTEM


4. Calculate the activity expected duration time
            
5.Calculate the cost per employee (Cem)and The total labor cost ( TLC )